An Example timetable of the Construction Process


(Starting after the building permit has been issued)


*Note: This particular schedule was for a simple 1000 sq.ft. home… this is a perfect scenario schedule. Winter construction and weather will affect/delay the timeline. The schedule listed is just to help homeowners understand the approximate sequence and process of building their home. A schedule is flexible so homeowners should not be surprised if their particular home does not follow this exact order.*

Week 1:
    Excavation
    Footings

Footings

Week 2:
    Concrete Block
    Waterproofing the Block
    Backfill


Week 3 and 4:
    Framing

Framing
Framing

Week 5:
    Roofing
    Heating, Plumbing & Electrical Rough-ins

Roofing
Plumbing rough-in
Plumbing rough-in
Electrical & Heathing rough-in

Week 6:
    Tyvek installed
    Temp. heat to thaw basement (winter construction)
    Insulation
    Drywall

Tyvek
Drywall

Week 7:
    Drywall
    Soffits and Facia
    Brick/Stone

Soffit & Fascia
Stone

Week 8:
    Drywall
    Trimwork
    Cabinets installed
    Concrete floors are poured

Trimming
Cabinets
Concrete Floors Poured

Week 9:
    Painting and Staining
    Countertops installed

Countertops

Week 10:
    Vinyl flooring installed
    Ceramic tile installed
    Laminate wood flooring installed
    Heating, Plumbing & Electrical finishes

Vinyl installed
Ceramic Tile
Laminate Wood Floor

Week 11:
    Heating, Plumbing & Electrical finishes
    Trimming finish
    Driveway installed
    Garage doors installed
    Siding

Electrical & Plumbing Finish
Driveway
Siding & Garage Doors

Week 12:
    Basement Insulation
    Carpet installed
    Final Clean
    Final Grade

Carpet

Week 13:
    Fire tape Garage
    Final Paint
    Landscaping
    Final Walk through

Final Paint
Landscaping

Week 14:
    Final Punch list
    Mortgage lender inspections


Week 15:
    Home ready for closing