An Example timetable of the Construction Process
(Starting after the building permit has been issued)
*Note: This particular schedule was for a simple 1000 sq.ft. home… this is a perfect scenario schedule. Winter construction and weather will affect/delay the timeline. The schedule listed is just to help homeowners understand the approximate sequence and process of building their home. A schedule is flexible so homeowners should not be surprised if their particular home does not follow this exact order.*
Week 1:
Excavation
Footings
Week 2:
Concrete Block
Waterproofing the Block
Backfill
Week 3 and 4:
Framing
Week 5:
Roofing
Heating, Plumbing & Electrical Rough-ins
Week 6:
Tyvek installed
Temp. heat to thaw basement (winter construction)
Insulation
Drywall
Week 7:
Drywall
Soffits and Facia
Brick/Stone
Week 8:
Drywall
Trimwork
Cabinets installed
Concrete floors are poured
Week 9:
Painting and Staining
Countertops installed
Week 10:
Vinyl flooring installed
Ceramic tile installed
Laminate wood flooring installed
Heating, Plumbing & Electrical finishes
Week 11:
Heating, Plumbing & Electrical finishes
Trimming finish
Driveway installed
Garage doors installed
Siding
Week 12:
Basement Insulation
Carpet installed
Final Clean
Final Grade
Week 13:
Fire tape Garage
Final Paint
Landscaping
Final Walk through
Week 14:
Final Punch list
Mortgage lender inspections
Week 15:
Home ready for closing